October 6, 2017 – Rosewood Lakes Update


Warning: count(): Parameter must be an array or an object that implements Countable in /home/southeas/public_html/wp-content/plugins/q-and-a/inc/functions.php on line 252

RTC Crews Unclog Culvert at Rosewood Lakes Golf Course

The Regional Transportation Commission (RTC) and Granite Construction worked together today to address rising wetland waters at Rosewood Lakes Golf Course. Crews have identified and remedied the source of the rising water and the water is receding. Wetland waters did not reach local residences.

Crews discovered that two 18-inch pipes/culverts within the golf course, outside of construction limits, were clogged with debris. The debris caused the water flowing through the golf course to spill onto a golf cart path. Granite Construction employees removed the debris and installed a small, temporary berm along the golf cart path.