Huffaker Bridge Progresses

Looking south at construction of the underside of the Huffaker Bridge.

Dear Stakeholder:

Crews have been at work constructing the Huffaker Bridge, and to show progress, the project team has created a flyover time-lapse video of bridge construction. The Huffaker Bridge is unique as it lies within a pinch-point between Rattlesnake Mountain and the Virginia Foothills, so it is designed extra-long to allow flood waters to spread out and reach the creek’s natural floodplain. Other interesting facts about the bridge include:

  • At 517-feet-long, it is the largest bridge being built on Phase 2 of the project.
  • Wire cables located inside the girders provide structural reinforcement that absorb the weight of the bridge.
  • Northbound and southbound lanes are constructed as two separate bridges that run side-by-side to allow sunlight in making driving underneath the structure brighter and safer.

Watch the Huffaker Bridge time-lapse on the ‘Videos’ page on the project website here. You can also subscribe to the SouthEast Connector Project and RTC Washoe channels on YouTube.


 For more information please call the project hotline at (775) 789-9832 or email Info@SouthEastConnector.com.  For additional information and to sign-up to receive updates visit SouthEastConnector.com