• July 14, 2017
    SouthEast Connector Project Hosts Summer Camp Group Dear Stakeholder: The SouthEast Connector project team partnered with the University of Nevada, Reno (UNR) College of Engineering Summer Camp this week to conduct an engineering field day. The summer camp group consisted Continue Reading...
  • July 7, 2017
    Curb and Gutter Poured at Pembroke Intersection Dear Stakeholder: The project team has made rapid progress on construction of the new Pembroke Drive and Veterans Parkway intersection. This week, concrete curb and gutter was poured on each side of Pembroke Continue Reading...
  • June 30, 2017
    Construction of Final Bridge is Underway Dear Stakeholder: Crews are busy at work constructing the final bridge on the project. The Huffaker Bridge, located at Alexander Lake Road, is the largest of five bridges being built on Phase 2 of Continue Reading...
  • Community Safety Notice
    June 23, 2017 Respecting Traffic Control in Work Zones Keeps Everyone Safe This week, the project team experienced a few frightening situations that put our workers’ lives at risk. A frustrated driver disobeyed multiple traffic stops on Mira Loma Drive Continue Reading...
  • June 23, 2017
    Cottonwoods Spread their Roots on the SouthEast Connector Project Dear Stakeholder: The project team has begun the planting of more than 600 trees, 569 of which are cottonwoods, throughout the project corridor. Segment 4 (between Clean Water Way and Pembroke Continue Reading...